National Reliability Officials Recommend Study of Additional Natural Gas Infrastructure to Maintain Reliability in Severe Cold

Published: February 27, 2024

By: Concentric Staff Writer

National reliability officials recommended a study of whether additional natural gas infrastructure, including new interstate pipelines and storage, is needed to maintain electric grid reliability in severe cold, among the lessons learned from Winter Storm Elliott that occurred in December 2022.

The study of additional infrastructure to support natural gas local distribution companies (LDC) was among the recommendations in the Joint Report on Winter Storm Elliott, which analyzed the severe cold weather event that took 1,700 generation units offline in the Eastern Interconnection. The report was jointly issued by the North American Electric Reliability Corporation (NERC), an industry-based group responsible for creating and enforcing national reliability standards, and the Federal Energy Regulatory Commission (FERC), an agency tasked with enabling reliable, safe, and economic energy service for U.S. consumers.

The NERC/FERC report recommends that an independent research group, such as national laboratories from the U.S. Department of Energy, should study possible infrastructure build-out as well as the associated costs.

“The purpose of the study would be to identify additional natural gas infrastructure needs, if any, needed to ensure the continued reliability of the electric and natural gas systems, and the preferred locations of such infrastructure, if applicable, including pipeline infrastructure, natural gas storage, and other supporting systems,” the report says. The study should also consider the needs in light of coincident peaks of LDC demand for natural gas for heating, as well as for demand from natural gas-fired power plants during long periods of abnormally cold weather, officials said.

“The study should analyze needs on a regional basis and consider current as well as forecast future needs, in light of our evolving and interdependent energy,” the report says. It should also look at whether there will be adequate natural gas infrastructure to accommodate the intermittence of new renewable energy resources and retirement of thermal generation resources, as well as recent patterns of natural gas production declines during severe weather events.

Other recommendations in the joint report include “prompt development and implementation” of revisions to reliability standards to strengthen generators’ performance during extreme cold weather; identification of generation units that are at the highest risk of problems in cold weather; assessments of freeze protection measure vulnerability; and engineering design reviews of units that have experienced cold weather outages. Also recommended is the identification of root causes of generation failures and a NERC/FERC study of the overall availability of “black-start” resources—units that can return to service quickly after a complete or partial shut-down.

Winter Storm Elliott, which plunged 18 percent of the Eastern Interconnection into outages, was just one of a series of major cold weather outages that struck the U.S. in recent years. While Elliott was the largest load shedding event in the Eastern Interconnection, the largest single such event was Winter Storm Uri in February 2021, which caused 20 gigawatts (GW) of load shedding by grid operators, mainly in Texas, and took out power for 4.5 million people, causing hundreds of deaths.

But the joint FERC/NERC report on Winter Storm Elliott points out that the situation in Texas during Winter Storm Uri and nearly a year later in the East during Elliott involved very different grids. What is more surprising is that the Winter Storm Elliott outages occurred in the highly connected Eastern Interconnection, unlike Texas, which has a grid almost completely isolated from both the Eastern Interconnection and Western Interconnection.1

“The quantity of firm load shed during Winter Storm Elliott was not as large as in the Winter Storm Uri event, but it is especially disconcerting that it happened in the Eastern Interconnection which normally has ample generation and transmission ties to other grid operators that allow them to import and export power,” the report says.

Winter Storm Elliott was characterized as both a bomb cyclone and an extra-tropical cyclone, moving from Upper Plains states in late December 2022, and hitting the East Coast on December 23 and 24. The cold and outages coincided with a spike in electricity usage causing many balancing areas in the East to declare energy emergencies (EEA). The 90.5 GW of unplanned outages stretched from Georgia to the Canadian border in the East and across the central U.S.

Similar to Uri, Elliott froze up natural gas system wellheads and other equipment, while the weather made maintenance and response impossible, leading to significant declines in natural gas production. There were reductions in gas pipeline pressure and 14 declarations of force majeure—unforeseen events that affect shippers’ ability to deliver gas on pipelines. Eight of 15 interstate pipelines queried for the report said there were 53 instances of power loss at facilities, totaling almost 467 hours. Outages averaged a few hours, although some went on for several days.

In the Northeast, pipeline operators reduced flows to other regions during Elliott and increased imports from Canada, while in the Southeast they increased outflows to the Midwest, decreased liquified natural gas (LNG) exports, and saw access to Northeast supply throttled. The Northeast in recent years has increased its production of natural gas, which normally leads to typical outflows of about 12.5 billion cubic feet per day (Bcf/d), but which were reduced to about 5.3 Bcf/d.

There were also some close calls. On the morning of December 24, Con Edison began experiencing drops in pipeline pressure and declared a gas system emergency, which included implementing specifications for curtailing users and reactivating an LNG regasification plant. Con Edison was in danger of cutting off some or all of its system users; even an outage of about 130,000 customers would have taken five to seven weeks to restore depending on the availability of mutual aid.

“Had it lost the majority of its system, over a million customers in New York City and nearby areas would have been unable to heat their apartments and houses while the outside temperature was in the single digits, for months,” the joint report says.

Outages at generation units are divided into broad categories in the report, including mechanical and electrical issues such as equipment failures, which formed 72 percent of these problems, and control system issues, which accounted for 12 percent. No other single sub-cause materially contributed to lost generation, the report says. Generators lost power as the coldness increased, including situations where generator gas or oil temperature became too low, metal components shrank, and oil viscosity in wind generators increased. The report notes that “a substantial majority” of generation units that reported freezing issues were operating at temperatures that were above the documented operating temperature requirements.

On December 24, 2022, gas production in the lower 48 states dropped to a low of 82.5 Bcf/d, a 16 percent decrease from December 21. The greatest declines in gas production were in the Marcellus and Utica shale formations. Generation outages began in the territory of the Southwest Power Pool (SPP) and MidContinent Independent System Operator (MISO). Neither regional transmission organization had to shed load, but SPP twice curtailed non-firm exports on December 23 because of lower reserves, and MISO and SPP began coordinating on regional directional transfer limits.

MISO declared an EEA 1 and EEA 2 on December 23. Tennessee Valley Authority (TVA) saw a rapid increase in generation unit outages early on December 23 and had lost 5 GW of generation by 6 a.m., causing it to declare EEA 1 and EEA 2. TVA began obtaining emergency power from Duke Energy, Southern Company, the PJM Interconnection, and MISO, but “this solution was short-lived,” the report says. These factors caused TVA to order firm load shed of 1,500 MW, about 5 percent of its system peak load.

Impacts on grid reliability due to cold weather are nothing new, and NERC has repeatedly warned of the risk. For instance, NERC and FERC in August 2011 issued a detailed joint analysis of an outage in Texas in February of that year that affected 1.3 million customer accounts, the “2011 Southwest Cold Weather Event.” 2 In an event similar to Winter Storm Uri that would occur a decade later, more than 4.4 million customer accounts were affected between February 2 and February 4, 2011, an event that also saw extreme natural gas delivery curtailments that were longer than electric customer outages because gas-fired equipment had to be relit.

More than 50,000 gas customers were affected in the 2011 outage, including more than 30,000 in New Mexico, along with customers in Arizona and Texas. That year, FERC and NERC launched a joint task force to inquire about the outages.

NERC and FERC listed capacity awareness, gas and electricity interdependency, transformer oil issues during cold weather, air duct icing, wind farm winter storm issues, rotational load shed, transmission facilities, and other factors as “lessons learned” from the 2011 Southwest Cold Weather Event.

In the joint NERC/FERC report issued in August of 2011, recommendations included that balancing authorities, reliability coordinators, transmission operators and generation owners and operators, in Texas and the Southwest view preparedness for winter as important as preparing for summer.

“The large number of generating units that failed to start, tripped offline, or had to be derated during the February event demonstrates that the generators did not adequately anticipate the full impact of the extended cold weather and high winds,” NERC and FERC said in the 2011 report. “While plant personnel and system operators, in the main, performed admirably during the event, more thorough preparation for cold weather could have prevented many of the weather-related outages.”

In a July 2013 report on previous cold weather events stretching back to 1983, NERC described six previous cold weather events in 1983, 1989, 2003, 2006, 2008, and 2010. There were also five cold weather experiences that caused operational challenges in February 1989, January 1994, January 2004, February 2006, and January 2007.

NERC and FERC said there were only three events that were comparable to the February 2011 Cold Weather Event in terms of load loss and generation outages. Those occurred in December 1983, December 1989, and January 1994.

In all the above events, however, there were two common themes observed: constraints on natural gas supply to power plants as well as generating unit trip-offs, derates, or failures to start due to cold weather due to problems like frozen sensing lines.

The first time ERCOT implemented load shedding region-wide was on December 21–24, 1989, when the grid operator shed 1.7 GW of firm customer load and curtailed natural gas supplies to generation units. The demand peak that occurred on December 22, 1989 was 12.4 percent above what was forecast. The temperatures during the 1989 cold weather event were the lowest in more than 100 years.

During those same days in December 1989, Florida also experienced extremely cold weather, which led to the curtailment of natural gas supplies. Record load of 34.7 GW due to the cold, combined with numerous generation units that were offline for maintenance, resulted in rolling blackouts of five to eight hours maximum. In both Texas and Florida, “the circumstances, size, geographic area, and impact on the bulk power system (BPS) of this event were deemed to be very similar to the February 2011 Cold Weather Event.,” NERC said.

NERC identified several familiar issues regarding the two incidents, including inadequate cold weather preparation, frozen ancillary plant equipment, fuel oil problems, and natural gas delivery curtailments. There were “numerous recommendations” for utilities in Florida and Texas, and certain corrective actions were undertaken by utilities.

NERC in the 2013 report said that common issues in the cold weather include the interdependence of the natural gas and electric systems, which continues to grow. Compressors used in the production and transportation of natural gas require electricity to operate.

Also, most generators purchase “non-firm” capacity, exposing them more to curtailments when supplies are tight, and there is competition between natural gas supply for electricity and natural gas for heating.

The cold weather outages that have struck the U.S. over the years have led to the development of cold weather reliability standards, which were issued by FERC in February 2023. The standards were developed from recommendations flowing from the joint inquiry into Winter Storm Uri to prevent such widespread outages from occurring again. NERC proposed the standards in October 2022, which include generator freeze-up protection measures, enhanced cold-weather preparedness plans, identification of freeze-sensitive equipment in generators, corrective actions for equipment freeze-ups, annual training for generator maintenance and operations personnel, and procedures to improve the coordination of load reduction measures during a grid emergency.

The FERC order implemented about half of the recommendations from the Winter Storm Uri FERC/NERC joint inquiry, and NERC is developing a second phase of the standards.

Though overall usage of natural gas for power generation might decline because of the transition to renewable energy such as solar and wind, the necessity of gas to balance the system against intermittent renewables could increase, the American Gas Association (AGA) said in a 2021 report entitled “How the Gas System Contributes to US Energy System Resilience.” But the current compensation model for gas is tied to the volume of gas delivered to power plants, which creates a disconnect between the value of the service and its compensation.

Natural gas infrastructure and replacement programs were designed to enhance reliability and safety, and have also contributed to “resilience,” defined as “as a system’s ability to prevent, withstand, adapt to, and quickly recover from system damage or operational disruption. Resilience is defined in relation to a high-impact, low-likelihood events.” The most common events that require a resilient grid are extreme weather events, the AGA report says.

The resilience needed to meet these challenges will be accomplished “through a diverse set of integrated assets,” the report says, adding that policies need to focus on optimizing the characteristics of both the electric and gas systems.

“Ensuring future energy system resilience will require a careful assessment and recognition of the contributions provided by the gas system,” the report says. “Utilities, system operators, regulators, and policymakers need new frameworks to consider resilience impacts to ensure that resilience is not overlooked or jeopardized in the pursuit to achieve decarbonization goals.”

Aside from the need for more natural gas system infrastructure for energy grid reliability and resilience, new pipelines are under construction to transport gas for export. There is more than 20 million Bcf/d of natural gas pipeline capacity under construction, partly completed or already approved to deliver gas to five liquefied natural gas export terminals that are under construction on the Gulf Coast, according to the U.S. Energy Information Administration.

FERC recently recognized the need to expand the natural gas system, approving in October a request by Gas Transmission Northwest LLC (GTN) to build and modify gas compressor facilities in Idaho, Washington, and Oregon (CP22-2).

“The proposed project will enable GTN to provide up to 150,000 [dekatherms per day] of firm transportation service on its existing system for delivery into Idaho and Pacific Northwest markets. We find that GTN has demonstrated a need for the GTN Xpress Project, that the project will not have adverse economic impacts on existing shippers or other pipelines and their existing customers, and that the project’s benefits will outweigh any adverse economic effects on landowners and surrounding communities,” FERC said in the order.

Another topic that has arisen in the wake of the outages is the need for reliability standards for the gas system, similar to what is in place for the electric system.

When FERC and NERC issued the final report on Winter Storm Elliott, FERC Chairman Willie Phillips in a written statement said: “I want everyone to take time during this Reliability Week to read this report and begin implementing these recommendations, particularly those addressing the interdependence of gas and electricity. The report highlights what I’ve called for before: Someone must have authority to establish and enforce gas reliability standards.”

NERC President and Chief Executive Officer Jim Robb said that the industry needs to implement the recommendations from the joint report as soon as possible.

“I echo the Chairman’s call for an authority to set and enforce winterization standards for the natural gas system upstream of power generation and local distribution,” Robb said in a written statement. “The unplanned loss of generation due to freezing and fuel issues was unprecedented, reflecting the extraordinary interconnectedness of the gas and electric systems and their combined vulnerability to extreme weather.”

 

1The three main components of the U.S. electric grid are the Eastern Interconnection, the Western Interconnection, and ERCOT.

2 Also referred to as the “February 2011 Cold Weather Event.”

All views expressed by the author are solely the author’s current views and do not reflect the views of Concentric Energy Advisors, Inc., its affiliates, subsidiaries, related companies, or clients. The author’s views are based upon information the author considers reliable at the time of publication. However, neither Concentric Energy Advisors, Inc., nor its affiliates, subsidiaries, and related companies warrant the information’s completeness or accuracy, and it should not be relied upon as such.

Newsletter Sign Up
 
Search
 
Follow